OL3 resumes electricity production after fixing glitch
Published : 27 Nov 2026, 00:05
Updated : 27 Nov 2026, 00:12
The Olkiluoto 3 (OL3) nuclear power plant resumed electricity production after repair work on Thursday, according to a press release issued by the owner of the plant Teollisuuden Voima Oyj (TVO).
The investigation and repair work at the plant unit was completed ahead of the original schedule, said TVO.
Electricity production at OL3 was interrupted on Thursday at 4:15 a.m. to investigate and repair a valve defect in a process system.
According to the original estimate, the investigation and repair work was expected to be completed by Saturday evening but it was completed earlier.
The valve defect was detected last Friday when the plant unit was increasing power following the outage. On Wednesday, OL3's power output was reduced to approximately 60 per cent to investigate the defect.
The authority shut down on Thursday just after eight days of resumption of power generation after maintenance outage following a glitch detected in a valve of the nuclear power plant.
The OL3 returned to electricity production on November 17 after 68 days of maintenance outage, which began on 10 September.