OL3 Nuke plant resumes power generation after 68 days outage
Published : 17 Nov 2026, 22:42
The Olkiluoto 3 (OL3) nuclear power plant returned to electricity production on Tuesday after 68 days of maintenance outage, said the owner of the plant Teollisuuden Voima Oyj (TVO) in a press release.
The plant was reconnected to the national power grid at 5:16 p.m. The ramp-up to full power will take about 80 hours.
The OL3 maintenance outage began on 10 September. The outage lasted longer than originally planned by 18 more days due to findings made during inspections and the resulting need for additional repairs.
Pump faults that had previously affected the plant’s electrical output were also repaired during the outage.
Additional work was carried out on components including valves where inspections had identified wear. The necessary repairs were completed thoroughly before restarting the plant for its next operating cycle.
OL3 will now begin an operating cycle of approximately 18 months before its next scheduled maintenance outage.
The most significant work included refueling and fuel inspections, maintenance and inspections of the main coolant pumps, and maintenance of electrical switchgear.
“This was my first OL3 maintenance outage in my new role, and I was particularly impressed by the strong commitment and professionalism of our own personnel. Together with our partners, we completed this extensive undertaking safely and to a high standard, providing a solid foundation for reliable electricity generation at OL3 over the next 18 months,” said TVO’s Senior Vice President of Maintenance, Marko Kesti.